This experiment is being conducted to assess temperatures, pressures, and materials proposed for trapping zinc in the tritium facilities. Revision …
E-Area Maintenance to Paint the 110 Gallon Drums Needed For Upcoming Work.…
Install biomass feedwater line support at 784-7A. The column will support the weight of the valve, transfer the load to the concrete floor and take…
The existing optional standby power system is original from the 1950's and has reached the end of its expected life. The optional standby diesel ge…
The existing standby power system is original from the 1950's and has reached the end of its expected life. The standby diesel generator and fuel t…
Evaluate and Correct Process Well 905-108H.…
707-3N and 707-4N Execute Post Civil work for 2 tornado shelters.…
731-4N Install Fans Inside Warehouse to Circulate Air.…
Relocate bench grinder to hot work area. Reroute conduit, power wires and install new local disconnect. Relocate belt sander into hot work area. In…
Replace asbestos containing insulation (clamshell) on strainer on the Chilled Water System, and reinsulate (with non-asbestos), K-Assembly Area.…