Replace 784-7A walking floor base plates.…
Renovate interior of Building 703-B, including but not limited to flooring, wall coverings, fixtures, etc. Replace Door No. 3 and remove door No. 4…
Piping in the Special Container Loading and Unloading (SCLU) system will be replaced with like-for-like piping due to the potential for mercury con…
Install a compressed air dryer in 248-H for the EDM in the machine shop.…
Construction group will be renovating 704-H.…
Remove and replace broken floor tiles in 724-H.…
The current method of filling the basin is an altitude valve designed to make up for large drops in basin level and not for routine smaller changes…
Remove carpet and cove base in 703-46A. Install LVP flooring and new cove base due to wear and tear at the limited area entrance of 703-46A.…
This work scope covers installing new flooring and cove base in building 717-8N.…
New stretch wrap machines will be installed at the 731-N Complex.…