The chilled water expansion tank failed testing and requires replacement. A new bladder tank, backflow preventer, and tie-ins for the system will b…
RMS-3 radiation detection units are going to be replaced with ARM-1000 units and the radio frequency communication system will be replaced with a h…
The L-Area Emergency Basin needs some additional electrical receptacles to support the Accelerated Basin Deinventory (ABD) Project.…
Leachate characterization and stabilization of bound PFAS in grout.…
780-1A Replace front doors and frame.…
Perform building improvements to process area at 782-3A.…
Subcontractor shall remove propane from the Lead Melter Propane Tank at 711-4N so Construction may replace the failed Rego manifold and test PRVs(P…
This Temporary Modification will install a Peterson Products Company Multi-Flex inflatable plug inside manhole P68 near the 234-H cooling towers.…
Restore Tank 709 level control to original design with new float style Kimray level controller (LC-415) in H Canyon.…
Subcontractor will repair 790-5B. The Subcontractor will not disturb the existing roof while performing these repairs on 790-5B.…