Paint and seal exterior of Building 722-5A. Scope also includes repairing stucco, installing aluminum plates at foundation, replacement of caulking…
Repair bypass line on Deepwell 905-53A. Pipe is cracked. Welding is required and a weld map is needed. Also repair V-007 broken valve handle.…
Paint and seal exterior of Building 720-2A. Scope also includes repairing stucco, caulking, and prepping the stucco for painting. Paint interior an…
Remove presumed asbestos containing material gaskets and replace PSV-001 on Soda Ash Pump 001 in Building 789-B.…
Remove presumed asbestos containing material gaskets and replace PSV-002 on Soda Ash Pump 002 in Building 789-B.…
Repair floors in Trailers 704-37E and 704-29E, including removal and replacement of floor and cove base.…
Valve H2-241125-FP-V-053 (Fire Protection Valve) will be replaced with a like-for-like valve. Valve is leaking. Remove and dispose of asbestos gask…
Remove all coatings down to the original concrete floor in Room 16 of Building 705-N.…
Remove soil saturated with diesel fuel at Building 703-A, C-Wing.…
The Subcontractor will caulk 30 feet at parapet/expansion joint to stop leaks at Building 284-20H. The Subcontractor will disturb the existing roof…