The chilled water supply to the breathing air compressor (No. 2) after-cooler/moisture separator has a developed a leak in the ceiling adjacent to …
Replace positive crankcase ventilation 001 outlet isolation valves A1-901-SW-V-428 & A1-901-SW-V-429 at 901-A. Valves are leaking. Gaskets will be…
Remove suspect asbestos gaskets on discharge line at 905-103F.…
This work supports HB area by including, dissolution, separation/purification of Pu/Np solutions which may contain Pu, U, Fe, etc., via ion exchang…
Americium will be electrodeposited onto a solid substrate from an acidic media. …
A Non-Time Critical Removal Action will consist of an emulsified oil permeable barrier. Trees and vegetation will be cleared and lay-down areas cre…
Remove and re-install insulation housing from secondary chill water pump 006 at Building 785-6A. The asbestos inspection report found insulation to…
Excavate and repair underground Service Water link near Building 784-A. Leak is due to normal wear and tear. Replacement materials will be like-for…
Replace packing in Deepwell Pump 905-108H. Treat packing/gaskets as asbesto…
This proposed activity will install a tie-in connection for an alternate diesel generator in the event of extensive repair time for the permanent i…