Replacement of AHU-B and AHU-C at 292-F. This will include disposal of old Air Handling Units.…
This proposed activity includes the installation of a new SAS storage bed and replacing the existing Carbon Steel Nitrogen Exhaust Line for the SAS…
General Powder/Solid Material Combination Studies to evaluate various combinations of powder/solid material for fabrication into a durable form.…
Welding repairs on Steam Lines.…
Subcontractor will provide roof repairs to Building 717-2B. The Subcontractor will not disturb the existing roof while performing these repairs on …
This activity installs a new vendor-designed, skid-mounted chemical feed system adjacent to the north side of the 285-11H Cooling Tower return flum…
Remove pressure relief valve H-284000-DW-PSV-001 on water heater located inside Building 284-H. Water heater is to be abandoned in place.…
Legacy insulation needs to be removed from Rm 602 in HB-Line. The insulation will be handled as asbestos.…
HB-Line will be entering Lay-Up status. The Process Air (PRA) system for HB-Line will not be needed to support the facility while in this configura…
Remove PACM gasket for hoist motor and repair emergency gate hoist 001 at L-Lake dam.…