Clean and apply Cool Seal coating to roofs of Trailers 704-31E, 33E, 37E, 49E, 50E, 51E, and 66E.…
Construction will perform light pressure wash and paint exterior of trailers (no scraping) on 704-49E, 704-50E, 704-51E, and 704-66E.…
754-5A Install vent pipe on top of diesel generator building.…
Remove and Replace Two Wooden Pedestrian Bridges to the South of Building 706-2F.…
Due to a demand for portable power in F-Tank Farm, 2 Diesel Generators have recently been processed for eligibility in our Reciprocating Internal C…
Remove Restroom Trailer 245-10F to the SRS Community Reuse Organization (CRO) laydown yard for future disposition.…
Replace Fire Alarm System in Building 703-47A.…
Remove out-of-service steam line section near 717-A.…
The purpose of this activity is to modify/improve mechanical properties for a thermosetting polymer extrusion process.…
Testing will be performed in the 773-A E-wing Shielded Cells to assess the impact of increased fissile loading in glass on glass durability.…