The objective of this work is to utilize soil columns to support an assessment of humate injection viability for remediation purposes. This activit…
Characterization of groundwater samples collected from SRS P-Area in support of remediation objectives will be performed at ACTL, 999-1W. Samples w…
Replace HVAC unit in 105-K MAC due to age, wear and tear.…
Replace the deck boards on the platforms and supporting structures on the Pond B weir boxes.…
Remove old valve pit cover and install new concrete cover at H7.…
Repair cracks, joints, and patchwork (spalling) on concrete intruder barrier at R-Area Seepage Basins (904-57G, 904-58G, 904-59G, 904-60G, 904-103G…
The Law Vault (LAWV) Cell process ventilation will be de-energized and the electrical power, controls, and associated alarms will be air-gapped. Th…
MCC-C Cubicle 3A, which feeds power to H-Canyon Center Section Exhaust Fan No. 3, experienced a catastrophic failure and needs to be replaced.…
Modify the 3rd level platform doors at 221-H.…
A 20 foot sealand/conex will be relocated from K-Area to SRPPF for use as a universal waste storage area.…