BPA proposes to maintain low growing vegetation communities in specific, localized areas in and adjacent to the Drummond-Macks Inn No. 1 and Green…
Install biomass feedwater line support at 784-7A. The column will support the weight of the valve, transfer the load to the concrete floor and take…
The existing optional standby power system is original from the 1950's and has reached the end of its expected life. The optional standby diesel ge…
The existing standby power system is original from the 1950's and has reached the end of its expected life. The standby diesel generator and fuel t…
Evaluate and Correct Process Well 905-108H.…
731-4N Install Fans Inside Warehouse to Circulate Air.…
Relocate bench grinder to hot work area. Reroute conduit, power wires and install new local disconnect. Relocate belt sander into hot work area. In…
Replace asbestos containing insulation (clamshell) on strainer on the Chilled Water System, and reinsulate (with non-asbestos), K-Assembly Area.…
766-H Renovate classrooms 1043,1045 and 1047. Remove items from wall, patch and prep walls to apply semi-gloss paint, remove carpet, prep floors, i…
Purchase a Caterpillar Excavator 320 equipped for mulching and tree clearing, to be utilized for mulching roadsides and runway areas to create effe…