Replace bearings for on chilled water pump at 235-2F. The presumed asbestos containing material (PACM) gasket material at the flanges will be remov…
Remove one Presumed Asbestos Containing Material (PACM) gasket from ABRP well AHT-14. Removal of gasket will allow for maintenance to repair broke…
Replace the Bartex level instrumentaiton for HB-Line Tank NT-31 with radar level instrumentation. Revision is being submitted to provide new dates…
Preparation of salt simulant solutions as well as cementitious waste forms that are representative of waste forms from SRS and offsite for testing…
A new metal-organic framework (MOF) will be tested for removing pertechnetate from a sample of SRS high level waste.…
SRNL is working to develop technology to perform imaging of processes conducted at the Savannah River Site. In this task we will perform imaging o…
Excavate to replace the defective domestic water valve DW-V-40 in H Area near 284-19H. Valve has failed between open and closed. …
Replace the tile flooring in the 701-1K Vestibule.…
Replace bearings for on chilled water at 285-11F. The presumed asbestos containing material (PACM) gasket material at the flanges will be removed.…
Excavate to correct the domestic water supply line leak at MOX Concrete Batch Plant.…