Excavating and constructing pad mounted electrical equipment for step down interconnection for the City of Luray to Western Cooperative.…
Fall River Rural Electric Cooperative plans to underground 3.22 miles of existing distribution lines in a heavily forested area in and next to Cari…
Rebuilding 2.75 miles of overhead transmission line in Atlantic Beach NC, includes: surveying, vegetation trimming, boring vertical holes to set n…
The City of Corwith plans a comprehensive grid resilience project that includes replacing approximately 158 wooden poles, 100 percent of crossarms,…
Purchase a Caterpillar Excavator 320 equipped for mulching and tree clearing, to be utilized for mulching roadsides and runway areas to create effe…
FEC plans to installation of a 1,000 kW/4,000 kWh containerized lithium-ion battery energy storage system (BESS) within the existing developed oper…
Wooden pole replacement (140)…
The City of Tipton's Resiliency Project is a two-part project, where part 1 affects specific areas of the city, part 2 affects the entire city. Pro…
Install the ADA technology at the Orsted Ford Ridge wind farm. The system will be designed to integrate with the plant's SCADA operational (OT) net…
This lab involves research applied towards geologic hydrogen, subsurface storage of hydrogen, carbon dioxide capture, carbon dioxide storage, and e…