Bradford Township replacement of existing Electric Substation facility will include excavation of a grounding grid, poured cement piers for substat…
The project objective is to develop a system engineering approach for produced water resource extraction and management in oil and gas operations.…
Installation of electronic reclosers. The majority will be installed on existing poles within rights-of-way while some instances of new poles withi…
Laboratory (corrosion) testing of chrome casing and tubulars for Coal Creek wells.…
Overhead to under-grounding conversion of approximately 10 miles of power line. …
This project is to change out two (2) poles and re-framing three (3) additional poles. The poles that need to changed out where discovered during o…
This project is to convert all the overhead lines to underground. This would include the primary lines and the secondary lines, this will not inclu…
This project start at Dixie Ave and Miller Blvd in Fruitland Park, FL. The reconductor will start at this intersection and go north to Spring Lake…
From US 27 and Carpenter St. starting at pole 209683, we are installing a new pole and installing our primary lines underground southwest to South …
BUECI plans to replace the gearbox on their existing Taurus generator which provides critical backup power for the community. …