The proposed solution addresses the requirements for the design, installation, and performance testing of replacing Diffuser (DI) System DE Vessel …
A Process Air pressure reducing station to operate pneumatic tools will be installed in the Saltstone Facility Process Room.…
The Saltstone Facility Bulk Material Handling (BMH) system is experiencing issues with the butterfly and knife gate valves.…
Install pipe support on 782-A bypass.…
Install new CAT 5 wiring at 66 drops in 703-1B.…
766-H Room 1029 Remove Carpet, Ceiling Tiles, and Wallpaper…
Remove the worn above ground drain pipe components of the GS level scupper drain pipe systems and replace them with similar new components.…
The subcontractor shall replace wooden line ties from the railroad bed, identified by site transportation and engineering as part of the 2022 scope…
Vacuum pump oil change at 999-1W.…
Run copper cable from 719-5N to 704-199N.…