Construction will take an asbestos sample from electrical enclosures in the 4th Level Control and Hot Gang Valve Corridor…
Analysis of water samples using liquid scintillation spectrometry.…
This Scope provides the labor, material, and services to install additional personnel office space and restroom for supporting new missions in K-Ar…
This EEC will cover pH, conductivity, and deuterium by FTIR methods as they apply to the analysis of basin water samples from K and L areas. This a…
This activity involves transferring an old office trailer to the SRSCRO and replacing it with a new trailer.…
Replace 914 Fan and 902 Fan Steam Condensate Quench Tank in K-Area…
The proposed action is for the closure of two underground storage tanks.…
Preparation work on TRU Pad 4 for installation of Non-Destructive Assay (NDA), Non-Destructive Evaluation (NDE), and Flammable Gas Analysis (FGA) e…
The Proposed Activity (PA) is to install temporary modification, 233H-TMC-19-280 via associated WOs 1745994 and 1752113, which would disconnect the…
Install new ATM Saphir 550 polisher/grinder assemblies and laboratory sink in 234-7H and D&R existing Buehler polisher/grinder assemblies. Replace…