Remove and replace floor tiles in select portions of the Purification Area within the K-Reactor, and prep and paint select wall locations.…
Repair and Replace Packing of 1 Steam Valve Outside of K-Area Purification and 2 Steam Valve Inside of Purification…
Make repairs to floor of 704-37E and 704-29E.…
Install additional receptacles in Building 736-A, Room 131.…
Install hands free water dispensers in 704-C, 703-43A, 704-N, and 703-46A.…
SRNL Research and Development Engineering will be conducting a fire suppression test in 723-A to support the Surplus Pu Disposition Project in K-Ar…
Venting or direct-shipment and disposal of specialty gas cylinders, nitrogen, carbon dioxide, compressed air, in A Area.…
Perform structural repairs on 772-F and 772-1F per the structural integrity program, SIP, inspection report T-CLC-F-00557.…
The subcontractor shall replace wooden line switch ties from the railroad bed, identified by site transportation and engineering as part of the 202…
Install Universal Wiring, UW, drops in Building 730-2B.…