Remove and install cove base in main corridors and foyers with same color/style. Prep and paint Room 125.…
Perform replacement of Rooftop Units (RTUs) #3, 4, 6, and 7B on the roof of Building 703-47A. The disconnect switch for RTU 9B will be replaced.
Remove west filter hold-down beam from 55 Elevation of the 105-L Building.…
A pre-built 12’ x 32’ storage building with be set up northwest of 782-4G in the Burma Road area. The purpose of the building is to store EC&ACP chem
The scope of this modification is to modify Building 773-42A to provide a new security boundary.…
Repair water damage in Building 705-N, Room 6.…
Remove and replace 931 condensate tank Pump A in -40 of 105-L.…
Seal K-Area sealand/seatrain roof with Blue Max sealant to prevent leakage.…
Existing high pressure sodium light fixtures in 233-H attic will be replaced with LED fixtures.…
Install a Shoreline Power drop in Building 709-7G for the reserve fire truck.…