The following work will be completed in the Functional Test Station (FTS): replace the filament and ion gauge for the Real Time Mass Spectrometer a…
At the A-Area Burning/Rubble Pits and Rubble Pit (731-A, -1A, and -2A)/Miscellaneous Chemical Basin/Metals Burning Pit (731-4A and -5A) Operable Un…
The DynaCool Physical property measurement system (PPMS) employs a minimum amount of condensed liquid Helium-4 for cooling both the sample chamber …
999-2W Liquid Nitrogen (LN2) Delivery System - Correct CHART Phase Separator and Replace LN2 Piping…
Upgrade men's and women's locker rooms in 704-K. Revision 1 is specific to the replacement of existing vinyl sheet flooring and extending work dura…
Replace Lift Station Pumps at 607-44H.…
Construction is to repair pipe penetration at 700 basin, as well as seal the joint where the basin wall meets the basin floor.…
This activity will correct/replace the internal components of 285-11H cooling tower cells that have worn due to normal wear and tear.…
Replace 248-H Wet Chemical Agent Cylinder due to Age…
Permeation testing of metal, ceramic, and polymer samples with hydrogen, deuterium, helium, argon, carbon monoxide, carbon dioxide, and nitrogen wi…