New substation, Electric Line, and Pole Replacement…
1.Reconfigure 41 miles of power line insulators 2. Reconductor 23 miles of transmission line 3. Relocate 2.1 miles of overhead conductors…
Grid automation upgrades with purchasing two mobile BESS to enable the grid flexibility and efficiency needed to achieve the goals and objectives.…
This project will investigate, deploy, and demonstrate the synergistic value of two types of Grid Enhancing Technologies (GETs): (i) DLR (SUMO), (i…
Install field sensors on existing utility poles. Develop a software tool that processes data from installed sensors and will be demonstrated in a u…
Substation construction/upgrades and electrical distribution lines upgrades. …
Replace existing electric distribution alley locations (3,900 feet of line, 36 poles, 28 transformers and three-phase conducter). Replace four exis…
Bonneville Power Administration (BPA) proposes to remove, replace, upgrade, and/or modify outdated equipment at Chief Joseph Substation and to repl…
The construction includes a 14MVA transformer, foundation and structural steel improvements, switches, disconnects, arrestors, bus, bus fittings, c…
The Western Area Power Administration (WAPA) Upper Great Plains Customer Service Region (UGP) routinely conducts activities that are part of the da…