Bonneville Power Administration (BPA) proposes to replace, upgrade, and/or install new substation and electronic equipment, oil containment, and an…
Bonneville Power Administration (BPA) proposes to re-conductor the Glade 115kV Tap serving Franklin County PUD (FCPUD) and Big Bend Electric Coop (…
The project will integrate ADMS/AEMS to command and control the electric distribution/transmission systems, update the GIS system to create a digit…
New substation, Electric Line, and Pole Replacement…
1.Reconfigure 41 miles of power line insulators 2. Reconductor 23 miles of transmission line 3. Relocate 2.1 miles of overhead conductors…
Grid automation upgrades with purchasing two mobile BESS to enable the grid flexibility and efficiency needed to achieve the goals and objectives.…
This project will investigate, deploy, and demonstrate the synergistic value of two types of Grid Enhancing Technologies (GETs): (i) DLR (SUMO), (i…
Install field sensors on existing utility poles. Develop a software tool that processes data from installed sensors and will be demonstrated in a u…
Substation construction/upgrades and electrical distribution lines upgrades. …
Replace existing electric distribution alley locations (3,900 feet of line, 36 poles, 28 transformers and three-phase conducter). Replace four exis…