1.35 miles of underground fiber installed in microduct within 4 inch HDPE conduit in existing Cooperative ROW. 1.49 miles of underground fiber ins…
PVREA plans to construct a microgrid that serves critical community facilities for a backup of approx. 40 hours. Critical facilities include a fir…
The USGFT project will purchase, install, and interconnect to existing substations battery energy storage systems (BESS) wih GFM inverters at multi…
The Project seeks to expand PPL's self-healing grid to support improved reliability and resiliency and, distributed energy resources and electric v…
Installation of two automated overhead switches and an IntelliNode device to self-heal the network in case of a circuit-level power outage.…
Installation of 47 GOABs throughout the electric system and installation of a line monitoring system.…
Replacing/upgrading existing electrical system improvements (switches, poles, etc.).…
Integrate 200MW of controllable load with the DERMS platform and associated programs.…
Adding down-line electronic reclosers on distribution power line wood poles and replacing reclosers in existing substations.…
Substation construction/upgrades and electrical distribution lines upgrades. …