The purpose of the requested grant funds is to facilitate the critical modernization of a recently acquired substation previously operated by Everg…
moving overhead distribution lines underground and wrapping transmission line poles in fire retardant mesh to reduce wild fire hazard in the Caribo…
Overhaul an existing generator unit by replacing the engine with a new engine of the same capacity. Perform engine testing prior to installation to…
Overhaul an existing generator unit by replacing the engine with a new engine of the same capacity. Perform engine testing prior to installation to…
The project will expand the existing network of fire-weather stations and wildfire detection cameras, and install AI-enabled grid monitors on feede…
Bonneville Power Administration (BPA) proposes to allow Dish Enterprise to install new wireless network antennas and equipment on structure 10/4 on…
The 34.5kV line will be rebuilt from the Attica interconnection meter to the substation which will include new oles, conductors, insulators, transf…
Maquoketa plans to underground a new line connected to the existing circuit and to increase the conductor size of the South Main Street Circuit Ris…
Pole Integrity, Preventative Vegetation Mgmt w/ an Intelligent Vegetation Mgmt System, Drone and AI- Enhanced Transmission Line Inspections/Repairs…
EREC has requested a 115kV bay addition at the WAPA Letcher Substation.…