MDU plans to construct a 230/46 kV addition to the Merricourt Transmission Substation to interconnect two new 46 kV sub-transmission lines, providi…
Bonneville Power Administration (BPA) proposes to move and raise four transmission structures in Federal Way, Washington to accommodate Sound Trans…
FEC plans to installation of a 1,000 kW/4,000 kWh containerized lithium-ion battery energy storage system (BESS) within the existing developed oper…
BPA is proposing to allow Pacificorp to mount four antennas on BPA's radio tower at the Sunnyside Radio Station, add coax/waveguide to the tower an…
The Western Area Power Administration (WAPA) Upper Great Plains Customer Service Region (UGP) routinely conducts activities that are part of the da…
This project will scale a single-stage (Type I) Solid State Transformer (SST), that has been demonstrated in single module operation, to a cascaded…
GVEA plans to take a comprehensive approach to prioritizing and hardening transmission poles in the interior of Alaska. With the use of drones, AI …
Bonneville Power Administration (BPA) proposes to replace and update electrical equipment at the existing Monroe Substation located about 3.2 miles…
Activities will include the proactive replacement of at-risk, aging, critical electrical infrastructure. Specific activities will include substatio…
Installation of new transmission poles and overhead line equipment in existing right-of-way and removing of existing poles and accessories. Replace…