The project scope includes the following, expand the yard to the southeast for a new 115-kV area, replace transformer KY1 A and relocate, construc…
Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), proposes to remove all WAPA-owned substation equipment at the Malta (MAL)…
Demolish existing electrical interconnect and install a pre-fabricated enclosure, switchgear, switching station, and support equipment.…
The US Department of Energy (DOE) proposes to modernize and expand the capacity of the LawrenceBerkeley National Laboratory (LBNL) Grizzly Peak Sub…
BPA proposes to interconnect Wheatridge Wind Energy, LLC’s 300-megawatt (MW) Ella Butte wind development project to BPA’s electrical transmission s…
At the Holcomb Substation near Holcomb, WA in Pacific County, BPA proposes to expand the existing fenced station yard and replace the existing powe…
The Western Area Power Administration (WAPA) is responding to an interconnection upgrade request by GridLiance West LLC (GridLiance) fo rebuilding …
Western Area Power Administration (WAPA), Rocky MountainRegion (RMR), proposes to approve an interconnection request from PacifiCorp (dba RockyMoun…
Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), proposes to replace and remove aging equipment at its Ault (AU) Substation i…
The Mission Support Contractor (MSC) and its subcontractors perform construction or modification of electric power substations or interconnection f…