This revision covers expanded testing locations along the powerline.…
Bonneville Power Administration (BPA) proposes to replace an existing 230-kilovolt (kV) shunt capacitor group and associated switching and protective equipment at Longview Substation near Longview, Cowlitz County, Washington (Township 8 North, Range 3 East, Donation Land Claim 38).
Bonneville Power Administration (BPA) proposes to allow Northern Wasco County Public Utility District (NWCPUD) to install about 1,500 linear feet of new 230kV transmission line on BPA fee-owned property in Wasco County, Oregon.
The US Department of Energy (DOE) proposes to perform assessment, modernization, and upgrade of the existing sitewide utility systems at the Lawren…
BPA proposes to replace structural components of the existing vehicle storage building at the Snohomish Substation with like materials and construction.
Bonneville Power Administration (BPA) proposes to allow Public Utility District No. 1 of Skamania County (Skamania PUD) to reroute an existing acce…
HMIS Annual Categorical Exclusion (CX) B4.11, Electric Power Substations and Interconnection Facilities for CY 2022…
This revision proposes an additional work area and identifies some temporary (in place for less than 6 months) test structures.…
BPA proposes to interconnect Avangrid’s 202-megawatt (MW) solar development project with BPA’s electrical system at Maupin Substation. …
BPA proposes to install generation metering and telemetry equipment for integration of a total 20-megawatt (MW) wave energy project.…