Removal of the 10-inch abandoned steam line, containing non-asbestos insulation per SDD-APG-2016-01366 asbestos inspection document. Steam pole rem…
A 9975 container is being heated to a temperature of up to 250F with external and internal heaters.…
Repaint and black out sections of parking lot.…
C. E. Bourne Subcontractor 00000611 will provide assembly and disassembly roof repairs at Building 105-L.…
Overhaul the diesel driven fire water pump at Building 901-Z due to normal wear and tear. Gaskets and packing material to be handled as potential a…
Remove PACM gasket for hoist motor and repair emergency gate hoist 001 at L-Lake dam.…
Perform repairs to Building 719-5N.…
772-F domestic water outlet isolation valve is leaking. In order to repair domestic water line near regulator, the presumed asbestos containing mat…
Install riprap on the upstream slope of Par Pond Dam between the existing riprap and the guard rail. The approximate width of the riprap addition i…
Replacement of AHU-B and AHU-C at 292-F. This will include disposal of old Air Handling Units.…