Storm drain piping in 105-L will be replaced.…
Reactor slugs and surrogate materials will be dissolved and tested in SRNL for off gas testing. Solution preparation and mock-up testing will be co…
Development of ionic liquids will be investigated in 935-W. Major activities include synthesis of ionic liquids (IL) with varying cation and anion …
Installation of fused disconnect to lower arc flash category of precipitator closet.…
B Area trailers 707-70B, 707-71B and 707-78B require electrical installation. This adds scope to prior NEPA evaluation to install the trailers.…
Construction of new gravel parking lot in B-Area.…
Install Trailer Landing Pads: E-Area Trailer Complex.…
The existing level transmitter is unreliable and causing numerous maintenance outages. It will be replaced with a radar sensor.…
Booster fan guardings in 221-H are inadequate and need to be replaced to address safety concerns.…
Remote Emergency Monitoring and Control System (REMACS) related equipment modifications are needed in 105-L. The old Remote Emergency Monitoring an…