Project 301 will remove old copper aerial line and replace with underground aluminum. This project consists of replacing 1,775 feet of aerial 4,160…
The proposed project is a 5MW/20MWh battery energy storage system (BESS), the construction of which includes minor grading, shallow foundations, an…
Overhead to underground conversion of ~1 and 1/2 miles of powerline. …
Wooden pole replacement (412)…
Wooden pole replacement (69)…
Overhead to underground conversion of ~1/2 miles of powerline.…
Overhead to underground conversion of ~2 miles of powerline. …
Southern Iowa Electric Coop will install line monitors and line fault indicators on substation feeders and critical locations to assist in monitori…
Franklin Rural Electric plans to replace an existing oil filled distribution hydraulic recloser with an S and C TripSaver II electronic recloser, a…
Design and commissioning of a medium voltage distribution transformer for testing. Synthesis of amorphous alloys, sensor fabrication, and testing f…