Remove water fountain and associated water filter from 247-H. Replace the water fountain with a bottle filling-water fountain combination.…
Shielding is to be installed around the Trim Cooler Fan Console Boxes to protect the operators when trying to access them.…
Install an additional check valve on the outlet of each primary purge compressor for the Chemical Process Cell (CPC) systems.…
The installation of a new guardrail system will provide fall protection from the edge of the roof for workers in the area or those passing by.…
The power feed to MFC-724/721 is provided from 3 50KVA pole mounted transformers by Harrison Blvd. Project plans on removing the pole mounted trans…
Disassemble and remove sections of nitrogen piping line NNG509 and install piping blinds.…
Propane supplied from the Flammable Gas Distribution System (FGDS) is no longer required throughout the facility and is only required for operation…
This project would replace identified equipment within the existing Building 12-123 Complex Compressed Air System with new equipment to meet the co…
Temporary rectifier is to be replaced with a permanent smaller rectifier for the S-Area Diesel Fuel Oil Underground Storage Tank and Underground Pi…
Two metal panels cover part of an expansion joint in the 105-L Disassembly Basin, in the Dry Cave portion of the basin area. These metal panelsare …