Replace boiler #3 in B39. Work includes removing existing boiler #3 including disconnecting all electrical and plumbing and installing new boiler i…
DOE LM is proposing to install aerial survey quality control monuments for future aerial survey activities at the Bear Creek, disposal site. Monume…
Remove four truck ramps utilized for KCRIMS transfer, regrade area, expand parking spaces, rework lighting and fire protection lines. September 20…
Chiller #1 is an air-cooled unit which requires periodic coil cleaning. The Site Stormwater SME has received approval from SCDHEC for release of c…
The proposed action would occur in two stages. The first stage would be installation of National Geodetic Survey-style monuments at four proposed l…
The proposed action would occur in two stages. The first stage would be installation of National Geodetic Survey-style monuments at four proposed l…
BPA proposes to perform in-kind replacement of wood pole structures and associated structural/electrical components (e.g. cross arms, insulators, g…
The Sikaflex sealer in the joints at the Heavy Water Component Test Reactor (HWCTR) have degraded. The existing material will be removed via wire w…
Subcontractor will provide roof repairs at Building 717-12F. The Subcontractor will not disturb the existing roof while performing these repairs on…
This proposed activity will repair damage to the 221-H roof in an HB-Line storage area resulting from scaffling being blown over during a storm eve…