Renovate the 264-1H Rm 151 kitchen with new flooring, paint, countertops, and cabinets.…
To provide building transition section, plenum, details for portable HVAC unit for 105-13K building.…
LED upgrade of exterior lighting of building 247-H…
Subcontractor will provide roof repairs at 717-F.…
This project includes replacement of the potable and fire water pipes on the NETL PGH R and D Plateau near the B-95 entrance gate and the Northeast…
BPA proposes to fund the Kalispel Tribe maintenance of habitat restoration projects in the Pend Oreille subbasin, where habitat has been degraded d…
BPA proposes to install cathodic protection for the water well to combat corrosion formed on the existing buried steel water well casement at its H…
This EEC covers various routine maintenance activities that occur in the buildings with the MOX Complex Area.…
Demo existing, rotting wooden structure and enclosure, SRS-PB-EX-0028, around compressor on south side of 731-2F.…
The doorway will be removed, widened, and replaced.…