Removal of spent blast material from the blast yard.…
ATTA Range 1 Berm slope repair.…
This work will remove water from the vacuum line between Building 779-A and Sand Filter stack, ICAMS enclosure.…
Replace Lift Station Pump 003 at 607-86G.…
Replace No. 003 Cooling Water Return Pump/Motor located at 281-2H.…
Replace flooring in M-15 lab and adjacent corridor due to radiological spill and contamination.…
Perform structural repairs on 772-F and 772-1F per the structural integrity program (SIP) inspection report T-CLC-F-00557.…
Construction personnel to remove/replace insulation around sump jet piping in Section 17 on the 2nd level.…
The scope of work for this activity is to remove the granite slabs from inside three culvert manholes, inspect the pipelines for any other blockage…
Melt cell high pressure sodium (HPS) light replacement with LED light for increased visibility.…