Construction is to prep and paint in the H and V room for the floor areas requiring re-painting.…
Repair wood beam in 711-9N.…
This EEC covers the evaluation and corrections of HVAC compressors units in 773-A.…
784-7A vendor to clean various locations in powerhouse.…
LM proposes to conduct routine inspections, maintenance, and monitoring activities, and real property and aviation actions at the Spook, Wyoming, U…
BPA owns and operates the 115 kV Bertelsen – Willow Creek No. 1 high voltage transmission line, which runs from Bertelsen Substation approximately …
702-A Install Keri door on entry No. 4.…
Construction is to paint the floors in the RRTAL cooldown room, electrical room, and protective clothing room as well as repair/paint the walls in …
Construction to excavate soil on west and north sides of 735-A, A-Wing Basement in order to repair existing underground commodity penetrations in t…
Repair 2 leaking roof drain pipes in 722-A.…