"The modification is being implemented to support the ""Layup"" plan to safely isolate or remove Structures, Systems, and Components (SSCs) no long…
This work scope is to set-up and operate a newly procured rope saw on the test wall at 666-E prior to utilizing in various areas across the site. T…
Due to a recent assessment of the air surveillance program at SRS, it has been decided to build a new air surveillance station to ensure thorough s…
Remove Portable Building 663-45G from service/use and excess it for transfer to SRS Community Reuse Organization (SCRO). A new building of the same…
241-280H Replace Manway on Tanks 01 & 02 and remove existing gaskets.…
This activity is to evaluate and correct lighting fixtures throughout Building 706-4F.…
Remove all coatings down to the original concrete floor in Room 16 of Bldg. 705-N.…
A 9975 container is being heated to a temperature of up to 250F with external and internal heaters.…
Removal of the 10-inch abandoned steam line, containing non-asbestos insulation per SDD-APG-2016-01366 asbestos inspection document. Steam pole rem…
Overhaul the diesel driven fire water pump at Building 901-Z due to normal wear and tear. Gaskets and packing material to be handled as potential a…