Six single-wide trailers will be removed and replaced with three new double-wide trailers near gate 16.…
B-Area replacing trailer doors due to water damage.…
The dust collector (Z-205000-BMH-DCOL-0002) for Silo No. 4 is to be replaced.…
Characterization of per- and polyfluoroalkyl substances (PFAS) source area soil contamination, well installation, and volatile organic compound (VO…
Flow sensors are planned for installation at two locations in D Area. One will be installed in the discharge canal (DSWM-8B) and D006 outfall (DSWM…
Install five (5) new monitoring and control points on existing utility poles in existing ROW.…
Rebuild three-phase Duke Energy line in existing ROW. Cut 1.1 miles of ROW along West McConnells HWY and install new single phase phase pole line …
Purchase of enhanced resiliency insulators and storm-hardened metal poles…
Installation of new equipment on existing poles that will allow a self healing network to automatically isolate and restore power, within seconds, …
Conversion of 4.0 miles of existing overhead distribution line from three-phase 4/0 ACSR to 477 ACSR on wooden poles using a spacer cable support s…