Bonneville Power Administration (BPA) proposes to correct 31 impairments along approximately 22 miles of the 115-kilovolt (kV) Grandview-Red Mounta…
BPA proposes to allow Clark PUD to remove transmission line conductors on one of their 7.2kV distribution lines where it crossed BPA ROW between To…
The Western Area Power Administration (WAPA) Upper Great Plains Customer Service Region (UGP) routinely conducts activities that are part of the da…
BPA proposes to rebuild and reconfigure a disconnect switch system along the Grandview-Red Mountain No. 1 Transmission Line at Prosser Tap. The Pro…
Bonneville Power Administration (BPA) proposes to rebuild three spans of the double-circuit Bell-Boundary No. 3 ꟷ Addy-Colville No. 1 transmission …
Bonneville Power Administration (BPA) proposes to upgrade, replace, and install new electrical station service and fiber optic cable networks acros…
Bonneville Power Administration (BPA) proposes to remove and add equipment at the Red Mountain Substation to interconnect new Benton Public Utility…
SWPA proposes to add a 200 MVA autotransformer at the Weleetka Substation. New foundations, conduits, and the installation of breakers, switches an…
All activities will occur within areas previously disturbed by construction and operation of WAPA and Basin Electric Coop facilities.…
BPA proposes to correct 25 impairments on the Big Eddy- Redmond 230-kV No. 1 line. The impairments encroach on the maximum allowed distance (MAD) b…