The DOE Loan Programs Office (LPO) is considering whether to issue a loan guarantee of a funding facility to the Alabama Power Company (APC) pursuant to its authority under the EIR 1706 Program.
Completion of full engineering design of a SCADA system for our electric distribution system and installation of SCADA electronic equipment at two …
Replacing electric poles to ensure more reliable service. Implementing monitoring systems at the Anson Substation. Strengthening infrastructure at …
To improve reliability and facilitate maintenance access, BPA proposes to expand and make related communication and equipment service upgrades at t…
Bonneville Power Administration (BPA) proposes to install electronic equipment and fiber optic cable at Boardman and Morrow Flat substations, rebui…
1. Install new substation conduit and manhole system for 13kv distribution. 2. Install new conduit and manhole system for 13kv distribution. 3. En…
Upgrading substation transformer and associated equipment within existing fencing of distribution substation. Also adding animal-deterrent fencing …
Site work to prep area for substation construction, including grading, stormwater, erosion control, material import, and compaction, ground grid in…
Installation of substation equipment…
The primary scope of this project involves upgrading obsolete electromechanical equipment (circuit breakers, relays, and regulator controls) within…