GPC proposes expansion of the existing Anthony Shoals substation and the installation of a new Status Synchronous Compensator (STATCOM) at the exis…
Rebuild a 69-kV transmission line, convert 30 segments of distribution lines from overhead to underground, and install OPGW communications infrastr…
This project plans to replace an aging 60kV transmission line with a new 115kV line approximately 7.9 miles in length. In addition to this line, op…
Construct 20'x60' structure in which Substation/Switchgearwill be installed. Excavate trenches for conduit installation between Power Plants and S…
Replacement of existing reclosers with new vacuum reclosers, Addition of auto-source transfer equipment on our existing distribution lines to impro…
Installation of new transmission poles and overhead line equipment in existing right-of-way and removing of existing poles and accessories. Replace…
The DOE Loan Programs Office (LPO) is considering whether to issue a loan guarantee of a funding facility to the Alabama Power Company (APC) pursuant to its authority under the EIR 1706 Program.
Completion of full engineering design of a SCADA system for our electric distribution system and installation of SCADA electronic equipment at two …
Replacing electric poles to ensure more reliable service. Implementing monitoring systems at the Anson Substation. Strengthening infrastructure at …
To improve reliability and facilitate maintenance access, BPA proposes to expand and make related communication and equipment service upgrades at t…