BPA proposes to demolish an aging 12.5kV control house and replace a 48VDC control voltage breaker. The new breaker would work with the 130VDC batt…
Bonneville Power Administration (BPA) proposes to update the existing Supervisory Control and Data Acquisition (SCADA), Sequential Events Monitor M…
Construction of a 34.5 - 14.4/24.94Y, 12/16/20 MVA substation including, but not limited to, disturbing an area of not more than two (2) acres by c…
BPA proposes to reconfigure bays and install new equipment inside the existing BPA Pearl Substation in Sherwood, Oregon. The proposed work would ac…
Installing new feeder lines from the switchgear to the substation transformer. …
Replacing 7 pad mounted transformers.…
Installation of about 300 miles of Fiber (which will mainly be for substation security systems) and Substation Security Systems – Cameras and addit…
The proposed Project aims to enhance the resilience and efficiency of Anaheim's electrical grid through strategic modernization efforts, including …
Bonneville Power Administration (BPA) proposes to expand the existing La Pine Substation near La Pine, Oregon to accommodate installation of three …
Installation of new battery monitoring equipment at 138 electrical substations that serve customers in Arkansas. …