Replace the deck boards on the platforms and supporting structures on the Pond B weir boxes.…
Remove old valve pit cover and install new concrete cover at H7.…
Repair cracks, joints, and patchwork (spalling) on concrete intruder barrier at R-Area Seepage Basins (904-57G, 904-58G, 904-59G, 904-60G, 904-103G…
MCC-C Cubicle 3A, which feeds power to H-Canyon Center Section Exhaust Fan No. 3, experienced a catastrophic failure and needs to be replaced.…
Modify the 3rd level platform doors at 221-H.…
Modification Traveler MT-TRI-2024-00012 will replace obsolete fire suppression system alarm check valves, deluge valve and strainers. The component…
Removal and Replacement of Modular Cubes and Carpet in 730-4B 2nd Floor Procurement Area.…
Subcontractor will repair 730-4B roof. The Subcontractor "will not" disturb the existing roof while performing these repairs on 730-4B.…
The 735-4B exterior light fixtures have been experiencing reliability issues and recent safety concerns have been raised by the building occupants …
Replace existing Enersys EC-7M batteries with new Enersys Absorbed Glass Mat (AGM) Batteries. Additionally, the existing battery rack shall be repl…