The scope of the General Plant Project funded Knolls Laboratory Building Z10 Emergency Generator Installation Project includes the design and inst....
The scope of the Radioactive Materials Laboratory (RML) Ventilation System Replacement Project is to replace all the filter housings and ductwork curr
Award Number: DE-EE0008916, CX(s) Applied: A9, B1.31, B3.6, Bioenergy Technologies Office, Location(s): FL, Office(s): Golden Field Office
The purpose of this Environmental Checklist (EC) is to address the redesign and installation of the new Advanced Test Reactor (ATR) Low Pressure Ai…
NEPA action levels for planned changes as defined in the Internal Procedure (IP00l)- How to Comply with the National Environmental Policy Act (NEPA…
The scope of this task will replace the diesel engine and generator and consolidate and or replace the existing 4 Motor Control Centers (MCCs) in R…
The Mission Support Contractor (MSC) and its subcontractors perform installation or relocation and operation of machinery and equipment (including,…
The proposed activity of this EC comprises two connected actions: • Replace several aging components of the ATR primary coolant system (PCS), and •…
This activity is to prepare and relocate various equipment from the MCA to off-site and on-site recipients.…
Proposed activity will reconfigure and remodel 226-2F to support use as a training and operations support facility.…