This activity is for completion of Safe Shutdown thru Phase 1 Deactivation of 237-H/238-H/238-1H facilities. Although individual building numbers, …
The proposed actions comprise maintenance support services frequently and routinely requested for operational support of DOE facilities and propert…
This activity is for completing a safe shutdown and deactivation process for F/H Lab (772-F, 772-1F and 285-3F). This process is required to prepar…
Receiving Basin Off-Site Fuel (RBOF) Cask Pad Containment Activities to include the action of evaluating items received and preparing for dispositi…
Water and Ethylene Glycol mixture from Drum 6 in 211-9F will be drained into Sanitary Sewer for treatment at Central Sanitary Wastewater Treatment …
LM is proposing to amend Categorical Exclusion Evaluation (CXE) Form LM 11-21 to conduct project-specific safeguarding activities at fourteen open …
The purpose of this plan is to implement a structured, phased approach to the safe and efficient disposal of scrap materials and waste stored at th…
The scope of work for this task is to Apply FireDam to fix contamination at the Transuranic Waste (TRU) Processing Facility located at Low Activity…
Install bird control netting/clean up and seal floor drains at Receiving Basin for Offsite Fuel (RBOF).…
All Uninterruptible Power Supply (UPS) systems not related to security or cranes will be removed from L-area.…