HB-Line will be entering Lay-Up status. The Process Air (PRA) system for HB-Line will not be needed to support the facility while in this configura…
This activity is for completing deactivation of the 236-H By-Product Facility. This facility includes the retired Burst Test Process, the He-3 Puri…
The purpose of F-DCF-H-00743 is to create an “Electrical Airgap” between Buildings 234-H and 236-H. Fire alarm and detection equipment within Build…
A single partial can of Leak-Tec 72V was found during a review of the gloveboxes as part of the facility lay-up preparations. Waste removed from t…
Deactivation of 690-N Ford Building and Ancillary Structures / Equipment in preparation for Decommissioning (Demolition) of the facility.…
The Diesel Generator is currently operationally OOS but has the capability to start possibly further damaging the diesel and downstream loads. The …
Air gapping of mechanical lines to isolate building 236-H. Rev 1 Incorporates an underground Fire Header to be air-gapped.…
Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), conducts routine maintenance activities at existing facilities in five stat…
The proposed action will replace a failed culvert that crosses the Argonne National Laboratory fence line, east of Kearney Road. The 30" diameter c…
The U.S. Department of Energy proposes projects to remediate and restore the Bayview Planning Area Parcel 1 (the Bayview Parcel 1 Cleanup Project) …