Until a mission is identified for the facility, HB-Line will be maintained in a layup state.…
Air gapping of mechanical lines to isolate building 236-H.…
Until a mission is identified for the facility, HB-Line will be maintained in a layup state.…
"The modification is being implemented to support the ""Layup"" plan to safely isolate or remove Structures, Systems, and Components (SSCs) no long…
Remove pressure relief valve H-284000-DW-PSV-001 on water heater located inside Building 284-H. Water heater is to be abandoned in place.…
HB-Line will be entering Lay-Up status. The Process Air (PRA) system for HB-Line will not be needed to support the facility while in this configura…
This activity is for completing deactivation of the 236-H By-Product Facility. This facility includes the retired Burst Test Process, the He-3 Puri…
The purpose of F-DCF-H-00743 is to create an “Electrical Airgap” between Buildings 234-H and 236-H. Fire alarm and detection equipment within Build…
A single partial can of Leak-Tec 72V was found during a review of the gloveboxes as part of the facility lay-up preparations. Waste removed from t…
Deactivation of 690-N Ford Building and Ancillary Structures / Equipment in preparation for Decommissioning (Demolition) of the facility.…