Westside Substation Additions (Amended)CX(s) Applied: B4.6Date: 05/25/2010Location(s): Idaho Falls, IdahoOffice(s): Bonneville Power Administration
Green Mountain Switchyard Stage 06 Spring 2010CX(s) Applied: B4.6, B4.11Date: 05/25/2010Location(s): ColoradoOffice(s): Western Area Power Administration-Rocky Mountain Region
Rattlesnake-Garrison Number-1 Wood Pole InstallationCX(s) Applied: B1.13, B4.6, B1.3Date: 05/13/2010Location(s): Missoula County, MontanaOffice(s): Bonneville Power Administration
Evaluation of Instrumentation and Dynamic Thermal Circuit Rating (DTCR) for Overhead LinesCX(s) Applied: B3.11, B4.6Date: 05/13/2010Location(s): St. Lawrence County, New YorkOffice(s): Electricity Delivery and Energy Reliability, National Energy Techno...
Installation of New Water System at Bonneville Power Administration Covington SubstationCX(s) Applied: B4.6Date: 05/12/2010Location(s): King County, WashingtonOffice(s): Bonneville Power Administration
Smart Grid Regional Demonstration - Technology Solutions for Wind Integration - Phase IICX(s) Applied: B1.19, B4.6, B5.1Date: 05/11/2010Location(s): Austin, TexasOffice(s): Electricity Delivery and Energy Reliability, National Energy Technology Laboratory
Kansas City Power and Light (KCP&L) Green Impact Zone Smart Grid DemonstrationCX(s) Applied: B4.6, A1, A9, A11, B1.7, B4.11, B5.1Date: 05/10/2010Location(s): Kansas City, MissouriOffice(s): Electricity Delivery and Energy Reliability, National Energy T...
Pinnacle Peak Substation Coupling Capacitor Voltage Transformer InstallationCX(s) Applied: B4.6Date: 05/10/2010Location(s): Maricopa County, ArizonaOffice(s): Western Area Power Administration-Desert Southwest Region
Redmond Substation 230-115-Kilovolt Transformer AdditionCX(s) Applied: B4.6Date: 05/07/2010Location(s): Deschutes County, OregonOffice(s): Bonneville Power Administration
Southwestern Power Administration proposes several switchboard and protective relaying control replacements to the Bull Shoals Dam (AR), Neosho (MO…