Lancaster Line and Load Project CX(s) Applied: B4.6, B4.7 Date: 06/28/2012 Location(s): Idaho Offices(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
June 28, 2012Lancaster Line and Load Project
CX(s) Applied: B4.6, B4.7
Date: 06/28/2012
Location(s): Idaho
Offices(s): Bonneville Power Administration
Bonneville Power Administration is proposing to add equipment to its existing Lancaster Substation, replace one transmission structure, modify one existing structure, and replace existing fiber optic cable.
CX(s) Applied: B4.6, B4.7
Date: 06/28/2012
Location(s): Idaho
Offices(s): Bonneville Power Administration
Bonneville Power Administration is proposing to add equipment to its existing Lancaster Substation, replace one transmission structure, modify one existing structure, and replace existing fiber optic cable.