Installation of approximately 6,000 ft. of 15 kV submarine distribution cable beneath the Fox Islands Thoroughfare in Penobscot Bay, Maine. 44.1325…
The Western Area Power Administration (WAPA), Desert Southwest Region is upgrading components of its Parker-Davis Project electrical transmission s…
A new 69 kV transmission line 4.0 miles long will be constructed from the existing Winlock substation (corner of SW Kerron St. and Hining Ave.) to …
Bury 2-miles of aerial single phase electrical line feeding the Kings Mountain State Park in existing right-of-way.…
Bury 3-miles of aerial three phase line feeding the Kings Mountain Nat'l Military and State Parks in existing right-of-way. Single-phase line feed…
Using directional boring techniques, install underground electrical distribution cable under state andfederal highways where presently overhead ele…
PVREA plans to construct a microgrid that serves critical community facilities for a backup of approx. 40 hours. Critical facilities include a fir…
The Native Village of Eagle plans to underground existing distribution lines from the Tribal-owned power station to the village store as well as gr…
The U. S. Department of Energy (DOE), Richland Operations Office (RL), Infrastructure and Services Division (ISD) proposes to modify the 13.SkV ele…
Cut 1000' ROW and install new 0.5 mile underground single phase tie line.…