The Knolls Laboratory L4 Pumphouse Sinkhole Repair Project is being undertaken to repair an existing concrete retaining wall along the edge of the Mohawk River where the river water flow is eroding the retaining wall and the surrounding shale rock face.
DOE proposes to construct, operate, and decommission a temporary compacted soil liner/cap test pad, which will include a soil borrow area, within the industrialized area at the Paducah Site located near Kevil in McCracken County, Kentucky.
The DOE Portsmouth/Paducah Project Office (PPPO) proposes to design and construct the C-107 Program Support Facility within the industrialized area at the Paducah Site located near Kevil in McCracken County, Kentucky.
The scope of the Bettis Laboratory North Campus Stormwater Project is to support the existing stormwater utility servicing the North Campus area which has met the system's service life.
Los Alamos County (County) proposes to install stormwater infrastructure in Subparcel A-8-a on County property to collect, manage, and send stormwater into Los Alamos Canyon located in Technical Area 02 on DOE/NNSA property south of DP road.
The scope of the Bettis Atomic Power Laboratory North Campus Utility Corridor Project is to support the existing Fire Water and City Water utility services to the North Campus area, which are currently supplied by a looped system that provides redundant service from two directions in the event of a localized system failure.
The U.S. Department of Energy (DOE) EM-LA is proposing to install stormwater controls within the 100-yr floodplains of Effluent, Mortandad, North Ancho, and Potrillo Canyons within Los Alamos National Laboratory (LANL) near Los Alamos, New Mexico.
East River requested a new bay addition at WAPA's Beresford Substation in South Dakota. …
The Central Alarm Station (CAS) is important for safe and effective operation of the Bettis Site. The CAS houses servers, computers, and monitoring equipment associated with systems to ensure safe operations.
Install a rainwater drain system along the 221-H East wall sections 7-18 to drain the rainwater on the roof to the stormwater system. …