The proposed activity is the abandonment of six (6) F-Canyon perimeter groundwater monitoring wells (FCA 2D, FCA 9D, FCA 10A, FCA 10D, FCA 16A, and…
As part of Athena project, NNSA is investing in infrastructure upgrades at SRNL to provide separation facilities. The clean Lab C-102 will be renov…
The project consists of a feasibility study of CPU's two existing backup generation units and assessment of future upgrade options, targeted upgrad…
The project will replace 100 poles across the system based on a previously conducted internal study. The project will also add components to operat…
To meet the project objective, PSCYC will invest in a new power transformer, which will serve as the primary voltage step-down device within a plan…
Replace copper conductors with aluminum conductors. Add monitoring equipment, control technologies, and replace oil filled reclosures with vacuum r…
Replace oil-filled reclosers with dual-voltage vacuum reclosers to allow for future voltage conversions. The reclosers as well as new oil-filled re…
The project scope includes vegetation management across approximately 200 miles of overhead distribution lines located within HSUD's service territ…
The project scope includes deployment of Supervisory Control and Data Acquisition (SCADA) and an Outage Management System (OMS) to modernize West …
Install SCADA and OMS at New Albany office and automation systems at the Blue Springs substation, Hickory Flat substation, NE New Albany substation…