Activities to support Tank Farm and DWPF with qualification of Sludge Batch 11.…
Project 4 - 1.9 mile project replaces an aging 80-year-old 2 ACSR three-phase line currently routed through private right-of-way with a new 4/0 alu…
Project 3 - Upgrade 1.7 miles of 4 ACSR three-phase line with new 336 ACSR or 4/0 aluminum line.…
Project 2 - Upgrade 3.2 miles of three-phase 2 ACSR line with new 4/0 aluminum line.…
Project 1 - Upgrade 9 miles of OH and UG 3-phase conductor.…
Project will consist of replacing all primary electric distribution wires, pole mounted transformers and wooden poles. The distribution system in t…
The scope of this project is the undertaking of a utility pole inspection and replacement project. This would allow the municipality to test, and t…
The City of Monett is replacing 50 utility poles and crossarms on a key distribution circuit to improve storm resilience and reduce outage risks. T…
MMU plans to convert aged overhead lines to underground. Underground primary and secondary wire will be installed and pad mounted transformers will…
Workers installing new hardware and insulators on power line, re-configuring single phase and three phase transformer banks, installing additional …