REPLACE 3836 RF METERS WITH AMI METERS. Install one 100' tower and base station.…
REPLACE 2909 RF METERS WITH AMI METERS. Install seven 100' towers and base stations.…
Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), proposes to conduct routine access road and transmission line right-of-way (…
East River Electric Power Cooperative (ERC) is upgrading the Arlington Tap facility on the WAPA Watertown - Brookings 115 kV transmission line. WAP…
WAPA would acquire additional land around Wessington Springs Substation to mitigate erosion from the substation and minimize damages from neighbori…
The proposed actions consists of adding a grounding transformer to the Woonsocket Substation. Staff would also move the fence between the gates out…
Characterization activities for CO2 storage complex to include: drilling USDW well, magnetic/electro- magnetic surveys, material testing, site mode…
Installing 225 Trip Saver Devices, Replacing 78 poles, and install 3 switches. …
Small samples (less than 100 mg) of porous aluminosilicate zeolite material are analyzed in an Autosorb iQ gas sorption analyzer manufactured by Qu…
The DOE Loan Programs Office is considering whether to issue a loan guarantee of a funding facility to the Alabama Power Company pursuant to its authority under the Energy Infrastructure Reinvestment 1706 Program.