The U.S. Department of Energy (DOE) is proposing to provide funding to Southern Company Services, Inc, (SoCo) to design and integrate a battery energy storage system (BESS) in an existing building and creating a distributed energy management system (DERMS) to link to existing distributed energy resources (DERs) with building loads.
Install SCADA and OMS at New Albany office and automation systems at the Blue Springs substation, Hickory Flat substation, NE New Albany substation…
Twin County EPA is proposing four integrated projects, reconductoring and constructing a 1.5-mile tie line between Refuge and Swiftwater substation…
The project will involve dismantling and removing the existing 70-year-old 13 kV substation equipment, including its single transformer, grounding …
The project scope includes deploying advanced protection equipment such as reclosers, relays, and sectionalizers that will isolate faults, minimize…
On SR 35, the project will construct circuit improvements that include the installation of 12 steel poles with concrete pads, high-capacity Aluminu…
The project consists of a feasibility study of CPU's two existing backup generation units and assessment of future upgrade options, targeted upgrad…
The project will replace 100 poles across the system based on a previously conducted internal study. The project will also add components to operat…
To meet the project objective, PSCYC will invest in a new power transformer, which will serve as the primary voltage step-down device within a plan…
Replace copper conductors with aluminum conductors. Add monitoring equipment, control technologies, and replace oil filled reclosures with vacuum r…