1. Rebuild 0.8 miles of electrical distribution line by removing the above ground cross-country (away from Hwy 43 roadside) electrical powerline an…

Office of NEPA Policy and Compliance

May 15, 2026
Estimated Read Time   min

1. Rebuild 0.8 miles of electrical distribution line by removing the above ground cross-country (away from Hwy 43 roadside) electrical powerline and installing underground electrical powerlines in the same right-of-way location.  2. Reconduct 2 miles of electrical distribution line from 50F3060 to BF463 by line trucks accessing the old wire, removing and replacing it with new wire. This may include a mix of work within the existing right-of-way as well as work in newly acquired right-of-way to move the line near the road. Poles along this line segment may be replaced as-needed. 3. Reconduct 1.6 mile of electrical distribution line from AF847 to 50Q0029 by line trucks accessing the old line.