This activity will modify the chemical feed system and associated concrete containment structures at the 789-B domestic water treatment plant.…
Repair walls, floor and seal roof of Trailers 735-10 and 735-9. Activities will require removal and replacement of damaged wood paneling, wall ins…
Five office trailers and one bathroom trailer in L-area will be removed and replaced.…
This design change (M-DCF-K-00585) will replace the 216-B sump pump and the associated discharge piping. Due to the existing anchor bolts in the su…
Removal of presumed asbestos containing material (PACM) gasket material at 784-7A Steam Plant in various flanged connections to allow for maintenan…
This activity details the general operation of the FormLabs Form2 SLA resin 3D printer along with the post-processing tasks associated with 3D prin…
Americium will be electrodeposited onto a solid substrate from an acidic media. Rev. 1 changes lab that work will be performed in.…
Refurbish F-Area entrance signs.…
Remove two presumed asbestos containing material (PACM) gaskets from Recovery Well 8 to allow for routine maintenance.…
Plutonium metal will be brought into SRNL for packaging in a long term configuration. Rev. 1 added Labs B135/139 to activity location.…