Upgrade Autotransformer components in existing substation, Replace distribution transformers in existing substation, and install 400 Tripsaver devi…
CarbonSAFE Phase III Project planning for site characterization for the Project's sequestration site via drilling appraisal wells and collection of…
Partnership of many to 1) focus on applied R and D to solve tech and non-tech flow battery tech, 2) focus on improving cost effectiveness of flow b…
Phase III CarbonSAFE project characterizing two storage facilities in Harris and Galveston counties, Texas.…
Replace existing electric distribution alley locations (3,900 feet of line, 36 poles, 28 transformers and three-phase conducter). Replace four exis…
Collection of acid mine drainage water to the Morris Number 2 Active Treatment Plant site operated by PA DEP. It is anticipated that up to 4 sample…
Project Management, Material Inventory and Analysis, LIBS Laboratory Testing, ML Modeling and Validation, Pilot-Scale testing in Fluidized Bed and …
The project conducts Raman and Laser-Induced Breakdown Spectroscopy experiments, develops prototype distributed laser sensing applications, and exp…
Replacing old transmission powerline feeding to Fairview City. And utilize the new line by installing a parellel transmission line for Mt. Pleasant…